Phase I

Phase 1 of the Rays of Hope project includes the construction of three classroom buildings - named Ray 1, Ray 4 and Ray 5 - along with essential structures including an office building, WC and water tank, road, fence, and electricity facilities. The inclusion of these particular structures in Phase 1 is in line with Thai government requirements for the establishment of a legally registered school, and will provide space for up to 300 students. Fundraising is taking place from 2025 to 2026, with construction set to take place from 2026 to 2027. The school is projected to open for its first academic year in May 2028.

Office

Office (A04) – 95 sq.m

The school office will provide a bright, clear space for school administration and teacher meetings. Located at the entrance of the school, the office will provide easy access for registration for parents and visitors.

THB 1,678,765.27
Euro 44,423.53

A04_Office.png

Ray 1

Ray 1 Building (A01) – 440 sq.m

The Ray 1 building is a 440 square metre space designed for the youngest of the Rays of Hope students. Positioned at the front of the school site, 5 classrooms will provide learning space for up to 150 students.

THB 4,903,936.79
Euro 129,768.11

A01_Ray 1 Building.png

Ray 4

Ray 4 Building (B02) – 192 sq.m

The Ray 4 building is located amongst shady trees in the centre of the school site. At 192 square metres, the building provides two classrooms.

THB 2,897,320.42
Euro 76,668.97

B02_Ray 4 Building.png

Ray 5

Ray 5 Building (B03) – 192 sq.m

The Ray 5 building will be located on the Western side of the school site. The sleek, open design of the two classrooms will provide a comfortable learning space for students.

THB 3,020,604.33
Euro 79,931.31

B03_Ray 5 Building.png

WC

WC (C03) – 72 sq.m

Modern toilets and wash stations will be located between the Ray 4 and Ray 5 buildings, providing easy access to students. There will be ten toilets for girls, and five toilets and four urinals for boys.

THB 1,263,574.56
Euro 33,436.74

C03_WC 2.png

THB 600,050,84
Euro 15,878.56

THB 1,308,132
Euro 34,615.82

THB 2,604,328.20
Euro 68,915.80

THB 1,112,681
Euro 29,443.79

THB170,000
Euro 4,498.54

Water Tank

Water Tank (C04) – 13 sq.m

The water tank, located at the rear of the school site, will ensure uninterrupted water access to students and staff throughout the academic year.

Road

Road (D01) – 1,432 m

Building the road is an essential part of ensuring access to education. The road will begin at the Southern entrance and branch out two ways, surrounding the school buildings to provide easy access to all.

Fence and Retaining wall

Fence and Wall (D02) – 365 m

The fence and wall will surround the entire school site - including buildings, car parking, and sports field - to ensure that students can learn in a safe and secure place.

Electricity

Electricity (D03)

Electricity is another core cost of preparing the school, constructing the facilities necessary to provide the electricity needed to run the school.

Drilling a well

This important cost will help to provide the school site with regular water.

ติดต่อ

ชอบสิ่งที่คุณเห็นหรือไม่ ติดต่อเราเพื่อเรียนรู้เพิ่มเติม

ฉันเป็นย่อหน้า คลิกที่นี่เพื่อเพิ่มข้อความของคุณเองและแก้ไขฉัน ฉันเป็นสถานที่ที่ยอดเยี่ยมสำหรับคุณในการบอกเล่าเรื่องราวและให้ผู้ใช้ของคุณรู้จักคุณมากขึ้นอีกเล็กน้อย

  • Facebook
  • Twitter
  • LinkedIn
  • Instagram

Thanks for submitting!

สำนักงานทะเบียน

info@mysite.com
โทร: 123-456-7890

info@mysite.com
โทร: 123-456-7890

สำนักงานรับสมัครนักศึกษา

info@mysite.com
โทร: 123-456-7890

© 2025 by Rays of Hope School. 

bottom of page